Common Issues in Steel Structure Installation and Preventive Measures


Excessive Deviation in Foundation Positioning Axes and Bearing Surface Elevation of Steel Columns
Causes:
Errors in foundation survey control network, measurement layout, and elevation setting
Insecure foundation formwork installation
Template displacement caused by high concrete pouring height or vibration impact
Use of uncalibrated measuring tools (steel tape, theodolite, level)
Misinterpretation of drawings or axis identification errors
Unconsolidated bearing surface without secondary finishing
Lack of fixation measures for embedded steel plates (or supports)
Concrete settlement and shrinkage
Consequences:
These deviations may lead to installation axis misalignment and support elevation errors, affecting overall structural installation quality.
Preventive Measures:
Measurement Control
Verify all instruments (levels, theodolites, measuring tapes) through calibration or metrological verification
Implement strict checking procedures for survey networks and layout
Formwork Installation
Ensure formwork possesses adequate strength and rigidity
Conduct periodic inspections during concrete pouring using measuring tools or plumb bobs
Immediately rectify any detected deviations before continuing work
Concrete Operations
Primary alignment: Before concrete placement
Secondary alignment: During concrete hardening
Perform secondary surface finishing and leveling before initial concrete setting
Implement two-stage alignment for embedded components:
Component Fixation
Install proper anchoring devices for base support plates or pedestals
Maintain position stability during concrete placement
Rectification Methods:
For minor deviations:
Column base adjustment
Bolt hole enlargement
Shim insertion
For significant deviations:
Conduct technical consultation with relevant parties
Develop and implement approved corrective
Quality Assurance:
Establish multi-stage inspection protocol (layout, formwork, embedding, final acceptance)
Maintain comprehensive construction records for traceability
Implement error prevention measures throughout the construction process